Mt Cotton Village Stage A9

Subdivisional Construction including clearing, earthworks, roadworks, retaining walls, stormwater, roofwater, sewerage and conduits. After completion of A9 stage, Brittwood was proud to be working on the next stage (A10&11) of subdivisional development at Mt Cotton. Stage A10&11 includes clearing, earthworks (8,000m3), roadworks( 2,000 sqm), retaining walls (700 sqm), stormwater(500m), roofwater, sewerage(400m) and conduits. Project was $1,532,000